73982 REL 101: 1996-083-00 EXP BIOP CTUIR GRANDE RONDE SUBBASIN RESTORATION 2020 |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Receipt of environmental compliance clearance from BPA | A: 165. Complete/initiate Environmental Permitting for Project Activities | 04/30/2022 | 04/30/2022 | |
Complete Longley Meadows Section 106 construction monitoring requirements. | B: 165. Conduct Section 106 Monitoring for Longley Project | 04/30/2022 | 04/30/2022 | |
Effective and consistent participation in Grande Ronde Basin Coordination | C: 191. Participate in Grande Ronde Basin Project Prioritization, Planning, and Coordination. | 04/30/2022 | 04/30/2022 | |
Evaluate and develop fish habitat enhancement project opportunities | D: 114. CTUIR Grande Ronde Subbasin Restoration Project Development and Coordination | 04/30/2022 | 04/30/2022 | |
Develop Project Design Drawings and Specifications | E: 174. Develop project designs and produce plans (Middle Upper Grande Ronde Phases 2 and 3) | 04/30/2022 | 04/30/2022 | |
Construction Management Complete | F: 100. Longley Meadows Fish Habitat Project Construction, Administration, Management, and Technical Observation/Inspection | 12/31/2021 | 12/31/2021 | |
Longley Meadows Habitat Complexity Additions | G: 29. Longley Meadows Habitat Complexity Additions | 12/31/2021 | 12/10/2021 | |
Conduct Fish Salvage Operations for Longley Meadows | H: 28. Longley Meadows Fish Salvage Operations | 10/15/2021 | 10/15/2021 | |
Construction Management Complete | I: 100. Middle Upper Grande Ronde River Fish Habitat Enhancement Project Construction, Administration, Management, and Technical Observation/Inspection | 10/22/2021 | 10/29/2021 | |
Maintain vegetation and control weeds on conservation projects | J: 198. Maintain Vegetation and Control Weeds on conservation projects | 04/30/2022 | 04/30/2022 | |
Conduct maintenance on McCoy, Dark Canyon, Meadow, Willow, Rock, Catherine Creek, and Grande Ronde River Projects | K: 186. Maintain instream structures, fences, and off-channel water developments | 04/30/2022 | 04/30/2022 | |
Pre-project and post evaluations | L: 186. Pre & post project evaluations | 04/30/2022 | 04/30/2022 | |
Participate in public outreach | M: 99. Public Outreach and Education | 04/30/2022 | 04/30/2022 | |
Administer Project | N: 119. Manage, Administer and Facilitate CTUIR GR Subbasin Restoration Project | 04/30/2022 | 04/30/2022 | |
Upload 2020 Annual Report | O: 132. 2020 Annual Report - May 2020 - April 2021 | 04/30/2022 | 04/30/2022 | |
Upload Completion Report | P: 141. Project Completion Reports for BPA | 04/30/2022 | 04/30/2022 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Complete/initiate Environmental Permitting for Project Activities | |||||||
B | 165 | Conduct Section 106 Monitoring for Longley Project | |||||||
C | 191 | Participate in Grande Ronde Basin Project Prioritization, Planning, and Coordination. | |||||||
D | 114 | CTUIR Grande Ronde Subbasin Restoration Project Development and Coordination | |||||||
E | 174 | Develop project designs and produce plans (Middle Upper Grande Ronde Phases 2 and 3) | 05/02/2020 | ||||||
F | 100 | Longley Meadows Fish Habitat Project Construction, Administration, Management, and Technical Observation/Inspection | |||||||
G | 29 | Longley Meadows Habitat Complexity Additions | 05/05/2021 | ||||||
H | 28 | Longley Meadows Fish Salvage Operations | 05/05/2021 | ||||||
I | 100 | Middle Upper Grande Ronde River Fish Habitat Enhancement Project Construction, Administration, Management, and Technical Observation/Inspection | |||||||
J | 198 | Maintain Vegetation and Control Weeds on conservation projects | 05/05/2021 | ||||||
K | 186 | Maintain instream structures, fences, and off-channel water developments | 05/05/2021 | ||||||
L | 186 | Pre & post project evaluations | 05/05/2021 | ||||||
M | 99 | Public Outreach and Education | |||||||
N | 119 | Manage, Administer and Facilitate CTUIR GR Subbasin Restoration Project | |||||||
O | 132 | 2020 Annual Report - May 2020 - April 2021 | |||||||
P | 141 | Project Completion Reports for BPA | |||||||
Q | 185 | Quarterly Status Reports |